Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Jun 2024 | 10 th and Part bill submitted. (1376 connections completed out of 2300 (801 HTCs and 575 FHTCs) | Vadanappilly AE | |
11 Jun 2024 | 10 th and Part bill submitted. (1376 connections completed out of 2300 (801 HTCs and 575 FHTCs) | Vadanappilly AE | |
23 Apr 2024 | 10 th and Part bill submitted. (1376 connections completed out of 2300 (801 HTCs and 575 FHTCs). | Vadanappilly AE | |
18 Apr 2024 | 10 th and Part bill submitted. (1376 connections completed out of 2300 (801 HTCs and 575 FHTCs). | Vadanappilly AE | |
08 Apr 2024 | 10 th and Part bill submitted. (1376 connections completed out of 2300 (801 HTCs and 575 FHTCs). | Vadanappilly AE | |
06 Apr 2024 | 10 th and Part bill submitted. (1354 connections completed out of 2300 (779 HTCs and 575 FHTCs). | Vadanappilly AE | |
25 Mar 2024 | 10 th and Part bill submitted. (1354 connections completed out of 2300 (779 HTCs and 575 FHTCs). | Vadanappilly AE | |
19 Mar 2024 | 10 th and Part bill submitted. (1354 connections completed out of 2300 (779 HTCs and 575 FHTCs). House connection work in progress. | Vadanappilly AE | |
14 Mar 2024 | 10 th and Part bill submitted. (1354 connections completed out of 2300 (779 HTCs and 575 FHTCs) | Vadanappilly AE | |
06 Mar 2024 | 10 th and Part bill submitted. (1354 connections completed out of 2300 (779 HTCs and 575 FHTCs) | Vadanappilly AE |