Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Dec 2022 | 775 FHTCs completed out of 2300, 7th and Part bill submitted. 250 mm DI and 350 mm DI Pipes laying progressed at Edathiruthy Gramapanchayath | Vadanappilly AE | |
19 Dec 2022 | 775 FHTCs completed out of 2300, 7th and Part bill submitted. 250 mm DI and 350 mm DI Pipes laying progressed at Edathiruthy Gramapanchayath | Vadanappilly AE | |
14 Dec 2022 | 765 FHTCs completed out of 2300, 7th and Part bill submitted. 250 mm DI and 300 mm DI Pipes laying progressed at Edathiruthy Gramapanchayath | Vadanappilly AE | |
12 Dec 2022 | 765 FHTCs completed out of 2300, 7th and Part bill submitted. | Vadanappilly AE | |
08 Dec 2022 | 692FHTCs completed out of 2300, 7th and Part bill submitted. | Vadanappilly AE | |
06 Dec 2022 | 677 FHTCs completed out of 2300, 7th and Part bill submitted. | Vadanappilly AE | |
02 Dec 2022 | 677 FHTCs completed out of 2300, 7th and Part bill submitted | Vadanappilly AE | |
28 Nov 2022 | 677 FHTCs completed out of 2300, 7th and Part bill submitted | Vadanappilly AE | |
25 Nov 2022 | 677 FHTCs completed out of 2300, 7th and Part bill submitted | Vadanappilly AE | |
21 Nov 2022 | 630FHTCs completed out of 2300, 7th and Part bill submitted | Vadanappilly AE |