Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Feb 2023 | 1171 connections completed out of 2300( 596 HTCs and 575 FHTCs) | Vadanappilly AE | |
31 Jan 2023 | 1070 connections completed out of 2300( 497 HTCs and 575 FHTCs) | Vadanappilly AE | |
27 Jan 2023 | 1070 connections completed out of 2300( 497 HTCs and 575 FHTCs) | Vadanappilly AE | |
23 Jan 2023 | 1014 connections completed out of 2300( 441 HTCs and 575 FHTCs) | Vadanappilly AE | |
20 Jan 2023 | 1014 connections completed out of 2300( 441 HTCs and 575 FHTCs) | Vadanappilly AE | |
16 Jan 2023 | 1010 connections completed out of 2300( 437 HTCs and 575 FHTCs) | Vadanappilly AE | |
09 Jan 2023 | 964 connections completed out of 2300( 391 HTCs and 575 FHTCs) | Vadanappilly AE | |
03 Jan 2023 | 952 connections completed out of 2300( 377 HTCs and 575 FHTCs) | Vadanappilly AE | |
30 Dec 2022 | 836 FHTCs completed out of 2300, 7th and Part bill submitted. 350 mm DI Pipes laying progressed at old post office road | Vadanappilly AE | |
26 Dec 2022 | 790 FHTCs completed out of 2300, 7th and Part bill submitted. 350 mm DI Pipes laying progressed at old post office road | Vadanappilly AE |