Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Apr 2022 | 463 FHTCs completed out of 2300,4th and Part bill submitted | Vadanappilly AE | |
01 Apr 2022 | 463 FHTCs completed out of 2300,4th and Part bill submitted | Vadanappilly AE | |
24 Mar 2022 | 318 FHTCs completed out of 2300,3rd and Part bill submitted | Vadanappilly AE | |
21 Mar 2022 | 273 FHTCs completed out of 2300,3rd and Part bill submitted | Vadanappilly AE | |
17 Mar 2022 | 246 FHTCs completed out of 2300,3rd and Part bill submitted | Vadanappilly AE | |
14 Mar 2022 | 215 FHTCs completed out of 2300,2nd and Part bill submitted | Vadanappilly AE | |
10 Mar 2022 | 184 FHTCs completed out of 2300,2nd and Part bill submitted | Vadanappilly AE | |
07 Mar 2022 | 184 FHTCs completed out of 2300,2nd and Part bill submitted | Vadanappilly AE | |
03 Mar 2022 | 163 FHTCs completed out of 2300,2nd and Part bill submitted | Vadanappilly AE | |