Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
20 Apr 2022 | Out of 3000 FHTCS , 2903 FHTCS are completed | Aralumoodu AE | |
19 Apr 2022 | Out of 3000 FHTCS , 2900 FHTCS are completed | Aralumoodu AE | |
18 Apr 2022 | Out of 3000 FHTCS, 2895 FHTCS are completed. | Aralumoodu AE | |
14 Apr 2022 | Out of 3000 FHTCS , 2885 FHTCS are completed | Aralumoodu AE | |
13 Apr 2022 | Out of 3000 FHTCS , 2880 FHTCS are completed. | Aralumoodu AE | |
12 Apr 2022 | Out of 3000 FHTCS , 2875 FHTCS are completed | Aralumoodu AE | |
07 Apr 2022 | Out of 3000 FHTCS , 2860 FHTCS are completed | Aralumoodu AE | |
05 Apr 2022 | Out of 3000 FHTCS, 2855 FHTCS are completed. | Aralumoodu AE | |
04 Apr 2022 | Out of 3000 FHTCS 2850 FHTCS are complrted. | Aralumoodu AE | |
30 Mar 2022 | 94% work completed.CC 12th and part bill for 2836 FHTCS are completed. | Aralumoodu AE |