| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 09 Sep 2023 | Work in good progress - 9.5 km completed out of 36.5 km and HTCs -150 no.s and 21 no.s | Kollam Project HD | |
| 08 Sep 2023 | Work in good progress - 9.5 km completed out of 36.5 km and HTCs -150 no.s and 21 no.s | Kollam Project HD | |
| 05 Sep 2023 | work in progress at PWD NH roads - 9km out of 35.6 Km completed and house connection works in progress..and Interconnection work progress at pookulam jn.. | Kollam Project HD | |
| 03 Sep 2023 | work in progress at PWD NH roads - 9km out of 35.6 Km completed and house connection works in progress...Interconnection completed in pozhikkara road... | Kollam Project HD | |
| 02 Sep 2023 | work in progress at PWD NH roads - 9km out of 35.6 Km completed and house connection works in progress | Kollam Project HD | |
| 01 Sep 2023 | work in progress at PWD NH roads - 9km out of 35.6 Km completed and house connection works in progress | Kollam Project HD | |
| 31 Aug 2023 | work in progress at PWD NH roads - 9km out of 35.6 Km completed and house connection works in progress | Kollam Project HD | |
| 28 Aug 2023 | work in progress at PWD NH roads - 9km out of 35.6 Km completed and house connection works in progress | Kollam Project HD | |
| 26 Aug 2023 | work in progress at PWD NH roads - 9km out of 35.6 Km completed and house connection works in progress | Kollam Project HD | |
| 25 Aug 2023 | Excavation and laying work in progress...House connection and backfilling work in progress.... | Kollam Project HD |