Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Oct 2023 Work in progress - 9.5 km completed out of 36.5 km .Fhtc work in progress...Excavation and laying progress...Backfilling and Geotagging progress... Kollam Project HD
30 Sep 2023 Work in progress - 9.5 km completed out of 36.5 km .Fhtc work in progress...Excavation and laying progress...Backfilling and Geotagging progress... Kollam Project HD
29 Sep 2023 Work in progress - 9.5 km completed out of 36.5 km .Fhtc work in progress...Excavation and laying progress...Backfilling and Geotagging progress... Kollam Project HD
28 Sep 2023 Work in progress - 9.5 km completed out of 36.5 km .Fhtc work in progress...Excavation and laying progress...Backfilling and Geotagging progress... Kollam Project HD
27 Sep 2023 Work in progress - 9.5 km completed out of 36.5 km .Fhtc work in progress...Excavation and laying progress...Backfilling and Geotagging progress... Kollam Project HD
26 Sep 2023 Work in progress - 9.5 km completed out of 36.5 km .Fhtc work in progress...Excavation and laying progress...Backfilling and Geotagging progress... Kollam Project HD
23 Sep 2023 Work in progress - 9.5 km completed out of 36.5 km ...house connection and geotagging progress...Leak rectification work in progress... Kollam Project HD
22 Sep 2023 Work in progress - 9.5 km completed out of 36.5 km ...house connection and geotagging progress... Kollam Project HD
21 Sep 2023 Work in good progress - 9.5 km completed out of 36.5 km and HTCs -150 no.s and 21 no.s fhtc and Road backfilling work in progress... Kollam Project HD
20 Sep 2023 Work in good progress - 9.5 km completed out of 36.5 km and HTCs -150 no.s and 21 no.s fhtc work in progress... Kollam Project HD