| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Oct 2023 | Work in progress - 11 km completed out of 36.5 km .Excavation and laying ...Backfilling work in progress... | Kollam Project HD | |
| 12 Oct 2023 | Work in progress - 11 km completed out of 36.5 km .Excavation and laying ...Backfilling work in progress... | Kollam Project HD | |
| 11 Oct 2023 | Work in progress - 11 km completed out of 36.5 km .laying and chamber work in progress...Leak work in progress... | Kollam Project HD | |
| 10 Oct 2023 | Work in progress - 11 km completed out of 36.5 km .laying and chamber work in progress...AC pipe plugging completed at Over Bridge junction in Paravoor- Chathannore road (left side).. | Kollam Project HD | |
| 09 Oct 2023 | Work in progress - 11 km completed out of 36.5 km .laying and chamber work in progress... | Kollam Project HD | |
| 06 Oct 2023 | Work in progress - 11 km completed out of 36.5 km .Fhtc work in progress...excavation and laying progress...Valve fixing work in progress...Interconnection work in progress... | Kollam Project HD | |
| 05 Oct 2023 | Work in progress - 11 km completed out of 36.5 km .Fhtc work in progress...excavation and laying progress...Road restoration work in progress...@ Manjadimoodu | Kollam Project HD | |
| 04 Oct 2023 | Work in progress - 9.5 km completed out of 36.5 km .Fhtc work in progress...excavation and laying ,road backfilling work in progress... | Kollam Project HD | |
| 03 Oct 2023 | Work in progress - 9.5 km completed out of 36.5 km .Fhtc work in progress...Excavation and laying and Geotagging progress...Interconnection work in progress... | Kollam Project HD | |
| 02 Oct 2023 | Work in progress - 9.5 km completed out of 36.5 km .Fhtc work in progress...Excavation and laying and Geotagging progress... | Kollam Project HD |