| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Aug 2023 | Total distribution laid 7 km out of 36.5 km..Excavation and laying work in progress.. Valve chamber and connection work in progress...Road backfilling progress... | Kollam Project HD | |
| 12 Aug 2023 | Total distribution laid 7 km out of 36.5 km..Excavation and laying work in progress.. Valve chamber work in progress...Htc work in progress at pozhikkara road... | Kollam Project HD | |
| 11 Aug 2023 | Total distribution laid 6 km out of 36.5 km..Valve chamber work in progress...Road backfilling and GI work in progress. | Kollam Project HD | |
| 10 Aug 2023 | Total distribution laid 6 km out of 36.5 km..Valve chamber work in progress...Road backfilling and GI work in progress. | Kollam Project HD | |
| 09 Aug 2023 | Total distribution laid 6 km out of 36.5 km..Valve chamber work in progress...Road backfilling and GI work in progress. | Kollam Project HD | |
| 08 Aug 2023 | Total distribution laid 6 km out of 36.5 km..House connection work in progress..DI pipe gap filling work in progress in Paravoor- Varkala road (right side)...Valve chamber work in progress... | Kollam Project HD | |
| 07 Aug 2023 | Total distribution laid 6 km out of 36.5 km..House connection work in progress...Excavation and laying work in progress... Interconnection work in progress.. | Kollam Project HD | |
| 05 Aug 2023 | Total distribution laid 6 km out of 36.5 km...fhtc progress..excavation and laying work in progress..DI gap closing work in progress Paravoor - Varkala road | Kollam Project HD | |
| 04 Aug 2023 | Total distribution laid 6 km out of 36.5 km...fhtc progress..excavation and laying work in progress.. | Kollam Project HD | |
| 03 Aug 2023 | Total distribution laid 6 km out of 36.5 km...fhtc progress..Interconnection and Excavation and laying progress... | Kollam Project HD |