Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Dec 2023 Work in progress in Paravur- Chathannoor road ... Interconnection and Laying progress..17.92km out of 36.50km.... Kollam Project HD
18 Dec 2023 Work in progress in Paravur- Chathannoor road ... Interconnection and Laying progress..17.92km out of 36.50km.... Kollam Project HD
14 Dec 2023 Work in progress in Paravur- Chathannoor road ...Side wall form work in progress Pukkulam Tank Kollam Project HD
13 Dec 2023 Work in progress in Paravur- Chathannoor road ...GI work and backfilling work in progress.chamber work in progress...Leak work in progress... Kollam Project HD
12 Dec 2023 Work in progress in Paravur- Chathannoor road ...GI work and backfilling work in progress..Interconnection and leak work in progress... Kollam Project HD
11 Dec 2023 Work in progress in Paravur- Chathannoor road ... Interconnection and Laying progress.. Kollam Project HD
06 Dec 2023 Work in progress in Paravur- Chathannoor road ... Interconnection and Laying progress.. Kollam Project HD
05 Dec 2023 Work in progress in Paravur- Chathannoor road ... Interconnection and DI work in progress... Kollam Project HD
29 Nov 2023 Payment remitted to PWD NH - 90 lakhs for road restoration @ paravoor - parippally , paravoor - chattanooga road and paravoor pozhikara road work. Today laying work started at paravoor - Chattanooga road Kollam Project HD
28 Nov 2023 Payment remitted to PWD NH - 90 lakhs for road restoration @ paravoor - parippally , paravoor - chattanooga road and paravoor pozhikara road work. laying work will start on 29.11.23 at paravoor - Chattanooga road Kollam Project HD