| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 08 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...19.50 km out of 36.50.Laying progress @ ward 3... Restoration work progress at ward 5 koonayil | Kollam Project HD | |
| 07 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...18.50 km out of 36.50.. Concrete breaking and Valve fixing work in progress... | Kollam Project HD | |
| 06 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...18.50 km out of 36.50.. Di work progress @ maniyamkulam- kutoor branch road..Concrete breaking and Valve fixing work in progress... | Kollam Project HD | |
| 05 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...18.50 km out of 36.50.. fhtc and Interconnection work in progress...2nd lift side wall form work in progress Pukkulam Tank.. | Kollam Project HD | |
| 04 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...18.50 km out of 36.50.. FHTC and Geotagging progress...GI and Concrete breaking progress... | Kollam Project HD | |
| 03 Jan 2024 | No Work | Kollam Project HD | |
| 02 Jan 2024 | Geo tagging work in progress at paravur | Kollam Project HD | |
| 01 Jan 2024 | No work | Kollam Project HD | |
| 31 Dec 2023 | Work in progress in Paravur- Chathannoor road...Laying completed...18.50 km out of 36.50k..GI and Interconnection work in progress...Maniyankulam-Kottoor road | Kollam Project HD | |