| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...20 km out of 36.5 Excavation work in progress Paravoor to Varkkala road | Kollam Project HD | |
| 17 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...20 km out of 36.50 ..Fhtc and Geotagging progress... | Kollam Project HD | |
| 16 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...20 km out of 36.50 ..Fhtc and Interconnection progress at ward 15 | Kollam Project HD | |
| 15 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...20 km out of 36.50 ..Fhtc workin progress... | Kollam Project HD | |
| 14 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...20 km out of 36.50 ..Fhtc work and interconnection progress... | Kollam Project HD | |
| 13 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...20 km out of 36.50 ..Fhtc work and interconnection progress... | Kollam Project HD | |
| 12 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...19.70 km out of 36.50 ..Fhtc work and interconnection progress... | Kollam Project HD | |
| 11 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...19.70 km out of 36.50 ..Fhtc work in progress... | Kollam Project HD | |
| 10 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...19.70 km out of 36.50 ..Tank Side wall 2nd lift Rcc work completed at pukkulam... | Kollam Project HD | |
| 10 Jan 2024 | Work in progress in Paravur- Chathannoor road...Laying completed...19.70 km out of 36.50 ..Interconnection progress... | Kollam Project HD |