Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Jun 2024 | pipeline work in progress. total pipe tobe laid 28 km, total pipe laid 21km. 870 Nos of HTC given, 723 HTC billed.Dt. of completion 30.04.2024 EOT requested up to 30.10.2024. | Kanhangad Proj Dn AE - 2 | |
26 Jun 2024 | pipeline work in progress. total pipe tobe laid 28 km, total pipe laid 21km. 870 Nos of HTC given, 723 HTC billed.Dt. of completion 30.04.2024 EOT requested up to 30.10.2024. | Kanhangad Proj Dn AE - 2 | |
26 Jun 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 21 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
24 Jun 2024 | pipeline work in progress. total pipe tobe laid 28 km, total pipe laid 21km. 870 Nos of HTC given, 723 HTC billed.Dt. of completion 30.04.2024 EOT requested up to 30.10.2024. | Kanhangad Proj Dn AE - 2 | |
21 Jun 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 21 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
19 Jun 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 21 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
17 Jun 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 21 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
14 Jun 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 21 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
12 Jun 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 21 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
10 Jun 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 21 km of pipeline laid | Kanhangad Proj Dn AE - 2 |