Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Jun 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 20 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
05 Jun 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
03 Jun 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
31 May 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
29 May 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
27 May 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
23 May 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
21 May 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
17 May 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
15 May 2024 | pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid | Kanhangad Proj Dn AE - 2 |