Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 May 2024 pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid Kanhangad Proj Dn AE - 2
03 May 2024 pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid. Kanhangad Proj Dn AE - 2
02 May 2024 ipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid. Kanhangad Proj Dn AE - 2
30 Apr 2024 Pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid. Kanhangad Proj Dn AE - 2
29 Apr 2024 Pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid. Kanhangad Proj Dn AE - 2
24 Apr 2024 Pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 19 km of pipeline laid. Kanhangad Proj Dn AE - 2
22 Apr 2024 Pipeline work in progress. 840 Nos of HTC given, 723 HTC billed. Kanhangad Proj Dn AE - 2
20 Apr 2024 Pipeline work in progress. 840 Nos of HTC given, 723 HTC billed. Kanhangad Proj Dn AE - 2
17 Apr 2024 Pipeline work in progress. 840 Nos of HTC given, 723 HTC billed. Kanhangad Proj Dn AE - 2
17 Apr 2024 Pipeline work in progress. 840 Nos of HTC given, 723 HTC billed. Kanhangad Proj Dn AE - 2