JJM Kasaragod district - Mogral Puthur Panchayath - WSS to Chengala, Muliyar, Mogral Puthur and Madhur Panchayaths - Reach 3 (Zone 9) - Laying Distribution and Providing FHTCs - from OHSR at Periyadukka
Project |
JJM Kasaragod district - Mogral Puthur Panchayath - WSS to Chengala, Muliyar, Mogral Puthur and Madhur Panchayaths - Reach 3 (Zone 9) - Laying Distribution and Providing FHTCs - from OHSR at Periyadukka |
Project Code |
KGDJJM092110759 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM Kasaragod district - Mogral Puthur Panchayath - WSS to Chengala, Muliyar, Mogral Puthur and Madhur Panchayaths - Reach 3 (Zone 9) - Laying Distribution and Providing FHTCs - from OHSR at Periyadukka |
Status |
On-going |
District |
Kasaragod |
Executing Office |
Kanhangad Project Division |
AS Amount (Rs) |
199000000
|
AS Number |
G.O (Rt)No.489/2021/WRD |
TS Amount (Rs) |
80000000 |
TS Number |
TS/2021-2022/2021/40448 |
Total Bill Submitted (Rs) |
2618409 |
Total Bill Paid (Rs) |
781737 |
Population Benefitted |
7600 |
Capacity in MLD |
0.25 |
Actual Project Completion Date |
01 Mar 2023 |
Coverage |
Azad Nagar,Blarkode,Eriyal,Adukath Vayal ,Periyadka,Bhagavathi Nagar,Paayichal,Badarppalli, etc.. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM - Kasaragod District - Mogral; Puthur Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 3(Zone 9)-Laying Distribution system and providing FHTCs- from OHSR at Periyadukka. |
Project Division Kannur ( KGD) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Jun 2024 |
pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 21 km of pipeline laid |
Kanhangad Proj Dn AE - 2 |
|
19 Jun 2024 |
pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 21 km of pipeline laid |
Kanhangad Proj Dn AE - 2 |
|
17 Jun 2024 |
pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 21 km of pipeline laid |
Kanhangad Proj Dn AE - 2 |
|
14 Jun 2024 |
pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 21 km of pipeline laid |
Kanhangad Proj Dn AE - 2 |
|
12 Jun 2024 |
pipeline work in progress. 870 Nos of HTC given, 723 HTC billed. 21 km of pipeline laid |
Kanhangad Proj Dn AE - 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
11/04/2022 |
Scheduled date of Completion of the Project |
01 Sep 2022 |
Expected date of Completion |
01/03/2023 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
10 Dec 2021 |