Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Dec 2023 | Pipeline work in progress.840 Nos of HTC given, 723 HTC billed. | Kanhangad Proj Dn AE - 2 | |
21 Dec 2023 | Pipeline work in progress.840 Nos of HTC given, 723 HTC billed. | Kanhangad Proj Dn AE - 2 | |
18 Dec 2023 | Pipeline work in progress.840 Nos of HTC given, 723 HTC billed. | Kanhangad Proj Dn AE - 2 | |
14 Dec 2023 | Pipeline work in progress.840 Nos of HTC given, 723 HTC billed. | Kanhangad Proj Dn AE - 2 | |
11 Dec 2023 | Pipeline work in progress.840 Nos of HTC given, 723 HTC billed. | Kanhangad Proj Dn AE - 2 | |
06 Dec 2023 | Pipeline work in progress.840 Nos of HTC given, 723 HTC billed. | Kanhangad Proj Dn AE - 2 | |
05 Dec 2023 | Pipeline work in progress.840 Nos of HTC given, 723 HTC billed. | Kanhangad Proj Dn AE - 2 | |
04 Dec 2023 | Pipeline work in progress. 18 km of pipeline laid.940 Nos of HTC given, 515 HTC billed. 4 Nos of FHTC given. | Kanhangad Proj Dn AE - 2 | |
02 Dec 2023 | Pipeline work in progress. 18 km of pipeline laid.940 Nos of HTC given, 515 HTC billed. 4 Nos of FHTC given. | Kanhangad Proj Dn AE - 2 | |
27 Nov 2023 | Pipe line work in progress. | Kanhangad Proj Dn AE - 2 |