Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Apr 2022 | FHTC Geotagged-2590 no.s (today's geotagged connections-0-nos) FHTC -Total-2593 nos.( today's physical connections-0 nos) total pipe laid - 1750 mtr | Kollam Project Dn AE | |
29 Apr 2022 | FHTC Geotagged-2590 no.s (today's geotagged connections-10-nos) FHTC -Total-2593 nos.( today's physical connections-0 nos) total pipe laid - 1750 mtr | Kollam Project Dn AE | |
28 Apr 2022 | FHTC Geotagged-2580 no.s (today's geotagged connections-4-nos) FHTC -Total-2593 nos.( today's physical connections-3 nos) total pipe laid - 1750 mtr | Kollam Project Dn AE | |
27 Apr 2022 | FHTC Geotagged-2576 no.s (today's geotagged connections-0-nos) FHTC -Total-2590nos.( today's physical connections-0 nos) total pipe laid - 1750 mtr | Kollam Project Dn AE | |
26 Apr 2022 | FHTC Geotagged-2576 no.s (today's geotagged connections-10-nos) FHTC -Total-2590nos.( today's physical connections-9 nos) total pipe laid - 1750 mtr | Kollam Project Dn AE | |
25 Apr 2022 | FHTC Geotagged-2566 no.s (today's geotagged connections-7-nos) FHTC -Total-2581nos.( today's physical connections-0 nos) total pipe laid - 1750 mtr | Kollam Project Dn AE | |
23 Apr 2022 | FHTC Geotagged-2559 no.s (today's geotagged connections-4-nos) FHTC -Total-2581nos.( today's physical connections-0 nos) total pipe laid - 1750 mtr | Kollam Project Dn AE | |
22 Apr 2022 | FHTC Geotagged-2555 no.s (today's geotagged connections-7-nos) FHTC -Total-2581nos.( today's physical connections-0 nos) total pipe laid - 1750 mtr | Kollam Project Dn AE | |
21 Apr 2022 | FHTC Geotagged-2548 no.s (today's geotagged connections-3-nos) FHTC -Total-2581nos.( today's physical connections-08 nos) total pipe laid - 1750 mtr | Kollam Project Dn AE | |
20 Apr 2022 | FHTC Geotagged-2545 no.s (today's geotagged connections-3-nos) FHTC -Total-2573nos.( today's physical connections-0nos) total pipe laid - 1750 mtr | Kollam Project Dn AE |