Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Nov 2023 | 29500m laying completed, 1435 connections completed, 14th and part bill submitted | Chavara AE | |
28 Oct 2023 | 29500m laying completed, 1431connections completed, 14th and part bill submitted | Chavara AE | |
25 Oct 2023 | 29500m laying completed, 1426 connections completed, 14th and part bill submitted | Chavara AE | |
19 Oct 2023 | 29500m laying completed, 1422 connections completed, 14th and part bill submitted | Chavara AE | |
16 Oct 2023 | 29500m laying completed, 1418connections completed, 14th and part bill submitted | Chavara AE | |
11 Oct 2023 | 29500m laying completed, 1415connections completed, 14th and part bill submitted | Chavara AE | |
07 Oct 2023 | 29500m laying completed, 1412connections completed, 14th and part bill submitted | Chavara AE | |
03 Oct 2023 | 29500m laying completed, 1409connections completed, 14th and part bill submitted | Chavara AE | |
27 Sep 2023 | 29500m laying completed, 1407connections completed, 14th and part bill submitted | Chavara AE | |
23 Sep 2023 | 29500m laying completed, 1407connections completed, 14th and part bill submitted | Chavara AE |