Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Apr 2022 | package 2- Reversed work order issued on 26/03/2022 | Malappuram PH Dn EE | |
19 Apr 2022 | package 4 - work order awarded on26/03/2022 package 5- work order awarded on 09/04/2022 | Malappuram PH Dn EE | |
16 Apr 2022 | Package 1 and Package 3 work ongoing, Package 1 99 FHTCs completed, Package 3 686 FHTCs completed | Mankada AE | |
11 Apr 2022 | Package 1 and Package 3 work ongoing, Package 1 97 FHTCs completed, Package 3 666 FHTCs completed | Mankada AE | |
07 Apr 2022 | Package 1 and Package 3 work ongoing, Package 1 26 FHTCs completed, Package 3 656 FHTCs completed | Mankada AE | |
02 Apr 2022 | Package 1 and Package 3 work ongoing, Package 1 23 FHTCs completed, Package 3 646 FHTCs completed | Mankada AE | |
30 Mar 2022 | Package 1 and Package 3 work ongoing, Package 1 20 FHTCs completed, Package 3 631 FHTCs completed | Mankada AE | |
26 Mar 2022 | Package 1 and Package 3 work ongoing, Package 1 15 FHTCs completed, Package 3 514 FHTCs completed | Mankada AE | |
23 Mar 2022 | Package 1 and Package 3 work ongoing, Package 1 10 FHTCs completed, Package 3 504 FHTCs completed. | Mankada AE | |
19 Mar 2022 | Package 3 work ongoing, 424 FHTCs completed | Mankada AE |