Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 May 2022 | package 2- Agreement executed on 07.04.2022 | Malappuram PH Dn EE | |
06 May 2022 | package 4- Agreement executed on 08.04.2022 package 5 - Agreement executed on 13.04.2022 | Malappuram PH Dn EE | |
04 May 2022 | Package 1 and Package 3 work ongoing, Package 1, 120 FHTCs completed, Package 3 740 FHTCs completed | Mankada AE | |
30 Apr 2022 | Package 1 and Package 3 work ongoing, Package 1 113 FHTCs completed, Package 3 736 FHTCs completed | Mankada AE | |
28 Apr 2022 | Package 1 and Package 3 work ongoing, Package 1 110 FHTCs completed, Package 3 726 FHTCs completed | Mankada AE | |
26 Apr 2022 | package 4- Agreement to be executed. | Malappuram PH Dn EE | |
26 Apr 2022 | package 5- Agreement to be executed. | Malappuram PH Dn EE | |
25 Apr 2022 | Package 1 and Package 3 work ongoing, Package 1 107 FHTCs completed, Package 3 706 FHTCs completed | Mankada AE | |
20 Apr 2022 | Package 1 and Package 3 work ongoing, Package 1 104 FHTCs completed, Package 3 696 FHTCs completed | Mankada AE | |
19 Apr 2022 | package 4 - Reversed work order awarded on26/03/2022 package 5- Reversed work order awarded on 09/04/2022 | Malappuram PH Dn EE |