Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Jan 2023 |
Package 3 completed ,Package 1 completed, Package 2, Package 4,and package 5 are work on going ,package 5-510 FHTCs completed , Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-702 FHTCs completed, Package 4-494 FHTCs completed |
Mankada AE |
|
03 Jan 2023 |
Package 3 completed ,Package 1 completed, Package 2, Package 4,and package 5 are work on going ,package 5-500 FHTCs completed , Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-702 FHTCs completed, Package 4-494 FHTCs completed |
Mankada AE |
|
29 Dec 2022 |
Package 3 completed ,Package 1 completed, Package 2, Package 4,and package 5 are work on going ,package 5-500 FHTCs completed , Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-702 FHTCs completed, Package 4-494 FHTCs completed |
Malappuram PH Dn EE |
|
28 Dec 2022 |
Package 3 completed ,Package 1 completed, Package 2, Package 4,and package 5 are work on going ,package 5-500 FHTCs completed , Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-702 FHTCs completed, Package 4-494 FHTCs completed |
Mankada AE |
|
28 Dec 2022 |
Package 3 completed ,Package 1 completed, Package 2, Package 4,and package 5 are work on going ,package 5-500 FHTCs completed , Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-702 FHTCs completed, Package 4-494 FHTCs completed |
Mankada AE |
|
21 Dec 2022 |
Package 3 completed ,Package 1 completed, Package 2, Package 4,and package 5 are work on going ,package 5-470 FHTCs completed , Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-460 FHTCs completed, Package 4-60 FHTCs completed |
Mankada AE |
|
12 Dec 2022 |
Package 3 completed ,Package 1 completed, Package 2, Package 4,and package 5 are work on going ,package 5-400 FHTCs completed , Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-278 FHTCs completed, Package 4-40 FHTCs completed |
Mankada AE |
|
25 Nov 2022 |
Package 3 completed ,Package 1 completed, Package 2, Package 4,and package 5 are work on going ,package 5-400 FHTCs completed , Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-265 FHTCs completed, Package 4-36 FHTCs completed |
Mankada AE |
|
16 Nov 2022 |
Package 3 completed ,Package 1 completed, Package 2, Package 4,and package 5 are work on going ,package 5-400 FHTCs completed , Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-220 FHTCs completed, Package 4-25 FHTCs completed |
Mankada AE |
|
11 Nov 2022 |
Package 3 completed ,Package 1 completed, Package 2, Package 4,and package 5 are work on going ,package 5-400 FHTCs completed , Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-220 FHTCs completed, Package 4-25 FHTCs completed |
Mankada AE |
|