Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Aug 2022 |
Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-400 FHTCs completed , Package 1- 468 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
16 Aug 2022 |
Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-80 FHTCs completed , Package 1- 468 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
11 Aug 2022 |
Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-62 FHTCs completed , Package 1- 462 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
08 Aug 2022 |
Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-62 FHTCs completed , Package 1- 462 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
06 Aug 2022 |
Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-33 FHTCs completed , Package 1- 462 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
03 Aug 2022 |
Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-33 FHTCs completed , Package 1- 462 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
30 Jul 2022 |
Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-30 FHTCs completed , Package 1- 462 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
27 Jul 2022 |
Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-15 FHTCs completed , Package 1- 455 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
25 Jul 2022 |
Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-15 FHTCs completed , Package 1- 455 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
21 Jul 2022 |
Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-5 FHTCs completed , Package 1- 449 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|