Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Aug 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-400 FHTCs completed , Package 1- 468 FHTCs completed, Package 3 -877 FHTCs completed Mankada AE
16 Aug 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-80 FHTCs completed , Package 1- 468 FHTCs completed, Package 3 -877 FHTCs completed Mankada AE
11 Aug 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-62 FHTCs completed , Package 1- 462 FHTCs completed, Package 3 -877 FHTCs completed Mankada AE
08 Aug 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-62 FHTCs completed , Package 1- 462 FHTCs completed, Package 3 -877 FHTCs completed Mankada AE
06 Aug 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-33 FHTCs completed , Package 1- 462 FHTCs completed, Package 3 -877 FHTCs completed Mankada AE
03 Aug 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-33 FHTCs completed , Package 1- 462 FHTCs completed, Package 3 -877 FHTCs completed Mankada AE
30 Jul 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-30 FHTCs completed , Package 1- 462 FHTCs completed, Package 3 -877 FHTCs completed Mankada AE
27 Jul 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-15 FHTCs completed , Package 1- 455 FHTCs completed, Package 3 -877 FHTCs completed Mankada AE
25 Jul 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-15 FHTCs completed , Package 1- 455 FHTCs completed, Package 3 -877 FHTCs completed Mankada AE
21 Jul 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-5 FHTCs completed , Package 1- 449 FHTCs completed, Package 3 -877 FHTCs completed Mankada AE