Status Date |
Overall Project Status |
Project Officer |
Contact |
16 Jul 2022 |
Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-2 FHTCs completed , Package 1- 446 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
12 Jul 2022 |
Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-2 FHTCs completed , Package 1- 446 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
07 Jul 2022 |
Package 3 completed ,Package 1, Package 2, and Package 5 work ongoing, Package 1- 417 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
29 Jun 2022 |
Package 3 completed ,Package 1, Package 2, and Package 5 work ongoing, Package 1- 417 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
25 Jun 2022 |
Package 3 completed ,Package 1, Package 2, and Package 5 work ongoing, Package 1- 414 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
23 Jun 2022 |
Package 3 completed ,Package 1, Package 2, and Package 5 work ongoing, Package 1- 412 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
18 Jun 2022 |
Package 3 completed ,Package 1, Package 2, and Package 5 work ongoing, Package 1- 162 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
15 Jun 2022 |
Package 3 completed ,Package 1, Package 2, and Package 5 work ongoing, Package 1- 148 FHTCs completed, Package 3 -877 FHTCs completed |
Mankada AE |
|
09 Jun 2022 |
Package 3 completed ,Package 1, Package 2, and Package 5 work ongoing, Package 1- 148 FHTCs completed, Package 3 -877 FHTCs completed. |
Perinthalmanna AE |
|
08 Jun 2022 |
Package 3 completed ,Package 1, Package 2, and Package 5 work ongoing, Package 1- 148 FHTCs completed, Package 3 -877 FHTCs completed. |
Mankada AE |
|