Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Nov 2022 Package 3 completed ,Package 1 completed, Package 2, Package 4,and package 5 are work on going ,package 5-400 FHTCs completed , Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-220 FHTCs completed, Package 4-25 FHTCs completed Mankada AE
26 Oct 2022 Package 3 completed ,Package 1 completed, Package 2, Package 4,and package 5 are work ongoing ,package 5-400 FHTCs completed , Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-198 FHTCs completed, Package 4-15 FHTCs completed Mankada AE
17 Oct 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-400 FHTCs completed , Package 1- 700 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-188 FHTCs provided, Package 2-15 FHTCs provided Mankada AE
07 Oct 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-400 FHTCs completed , Package 1- 681 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-187 FHTCs provided, Package 2-12 FHTCs provided Mankada AE
29 Sep 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-400 FHTCs completed , Package 1- 660 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-182 FHTCs provided, Package 2-2 FHTCs provided Mankada AE
19 Sep 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-400 FHTCs completed , Package 1- 617 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-182 FHTCs provided Mankada AE
14 Sep 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-400 FHTCs completed , Package 1- 607 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-182 FHTCs provided Mankada AE
05 Sep 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-400 FHTCs completed , Package 1- 528 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-182 FHTCs provided Mankada AE
01 Sep 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-400 FHTCs completed , Package 1- 528 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-150 Mankada AE
23 Aug 2022 Package 3 completed ,Package 1, Package 2, Package 4,and package 5 are work ongoing ,package 5-400 FHTCs completed , Package 1- 468 FHTCs completed, Package 3 -877 FHTCs completed Mankada AE