Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Mar 2023 | Conditional TS obtained. Land not obtained | Perambra PH Sn - AE | |
02 Mar 2023 | Conditional TS obtained. Land not obtained | Vadakara PH Dn EE | |
26 Oct 2022 | Land required for WTP and reservoirs not obtained. Survey work completed. Estimate for distribution submitted for approval | Perambra PH Sn - AE | |
21 Oct 2022 | Land required for WTP and reservoirs not obtained. Survey work completed. Estimate for distribution submitted for approval | Perambra PH Sn - AE | |
17 Oct 2022 | TS NOT ISSUED | Perambra PH Sn - AE | |
30 Aug 2022 | Work not Started. Land not handed over to KWA by beneficiary Panchayats. Distribution Survey work completed. | Perambra PH Sn - AE | |
09 Jun 2022 | Work not Started.Land not handed over to KWA by beneficiary Panchayats | Vadakara PH Dn EE |