27 Jun 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 96738m, HTC - 1219 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1162 FHTC - 0. Perambra PH Sn - AE
24 Jun 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 96738m, HTC - 1219 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1162 FHTC - 0. Perambra PH Sn - AE
21 Jun 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 96738m, HTC - 1219 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1152 FHTC - 0. Perambra PH Sn - AE
17 Jun 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 96738m, HTC - 1219 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1152 FHTC - 0. Perambra PH Sn - AE
11 Jun 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 96738m, HTC - 1219 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1152 FHTC - 0. Perambra PH Sn - AE
06 Jun 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 96726m, HTC - 1219 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1152 FHTC - 0. Perambra PH Sn - AE
03 Jun 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 96330m, HTC - 1204 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1110 FHTC - 0. Perambra PH Sn - AE
30 May 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 95874m, HTC - 1159 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1110 FHTC - 0. Perambra PH Sn - AE
27 May 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 95012m, HTC - 820 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1096 FHTC - 0. Perambra PH Sn - AE
23 May 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 94748m, HTC - 820 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1096 FHTC - 0. Perambra PH Sn - AE