Jal Jeevan Mission - WSS to Maruthonkara and Kavilumpara Panchayats

Project Jal Jeevan Mission - WSS to Maruthonkara and Kavilumpara Panchayats
Project Code CLTJJM022211009
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Supplying & Laying Distribution System in Kavilumpara & Maruthonkara Grama Panchayath in Kozhikode District.
Status On-going
District Kozhikkode
Executing Office Vadakara PH Dn
AS Amount (Rs) 930800000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 271000000
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 38875
Capacity in MLD 13.00
Actual Project Completion Date Date is not specified
Coverage Two Grama panchayats

Packages

No. Project Name Location View
1 Package I - Jal Jeevan Mission - WSS to Maruthonkara and Kavilumpara Panchayats - Supplying & Laying Distribution System in Kavilumpara & Maruthonkara Grama Panchayath in Kozhikode District Perambra PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Jun 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 96738m, HTC - 1219 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1162 FHTC - 0. Perambra PH Sn - AE
21 Jun 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 96738m, HTC - 1219 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1152 FHTC - 0. Perambra PH Sn - AE
17 Jun 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 96738m, HTC - 1219 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1152 FHTC - 0. Perambra PH Sn - AE
11 Jun 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 96738m, HTC - 1219 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1152 FHTC - 0. Perambra PH Sn - AE
06 Jun 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 96726m, HTC - 1219 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1152 FHTC - 0. Perambra PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project 31 Dec 2024
Expected date of Completion 31/12/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 25 Nov 2022

Other details

Project Officers View