Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Dec 2023 90mm ,110mm PVC laying work in progress .Total 54018m pipe laid - Maruthonkara GP. 90mm PVC laying work in progress. Total 55339m pipe laid ,Total House connection : 170 - Kavilumpara GP Perambra PH Sn - AE
03 Dec 2023 90mm ,110mm PVC laying work in progress .Total 49244m pipe laid - Maruthonkara GP. 90mm PVC laying work in progress. Total 55102m pipe laid ,Total House connection : 170 - Kavilumpara GP Perambra PH Sn - AE
30 Nov 2023 90mm ,110mm PVC laying work in progress .Total 48551m pipe laid - Maruthonkara GP. 90mm PVC laying work in progress. Total 54675m pipe laid ,Total House connection : 145 - Kavilumpara GP Perambra PH Sn - AE
27 Nov 2023 90mm ,110mm PVC laying work in progress .Total 48551m pipe laid - Maruthonkara GP. 90mm PVC laying work in progress. Total 54675m pipe laid ,Total House connection : 145 - Kavilumpara GP Perambra PH Sn - AE
24 Nov 2023 90mm ,110mm PVC laying work in progress .Total 47284m pipe laid - Maruthonkara GP. 90mm 8kg PVC laying work in progress. Total 54314m pipe laid ,Total House connection : 137 - Kavilumpara GP Perambra PH Sn - AE
21 Nov 2023 90mm ,110mm PVC laying work in progress .Total 41189m pipe laid - Maruthonkara GP. 90mm 8kg PVC laying work in progress. Total 54068m pipe laid ,Total House connection : 137 - Kavilumpara GP Perambra PH Sn - AE
18 Nov 2023 90mm ,110mm PVC laying work in progress .Total 41189m pipe laid - Maruthonkara GP. 90mm 8kg PVC laying work in progress. Total 54068m pipe laid ,Total House connection : 131 - Kavilumpara GP Perambra PH Sn - AE
15 Nov 2023 90mm ,110mm, 140mm PVC laying work in progress .Total 39053 M - Maruthonkara GP, 90mm PVC laying work in progress. Total 53678 M ,Total House connection : 125 - Kavilumpara GP Perambra PH Sn - AE
12 Nov 2023 90mm ,110mm, 140mm &160mm PVC laying work in progress Maruthonkara GP Total House connection : 118 - Kavilumpara GP Perambra PH Sn - AE
09 Nov 2023 90mm ,110mm, 140mm &160mm PVC laying work in progress Maruthonkara GP Perambra PH Sn - AE