Status Date Overall Project Status Project Officer Contact
11 Jan 2024 Maruthonkara GP - pipeline as per estimate - 160945m, laid - 71933m, HTC - 0 FHTC - 0 Kavailumpara GP - pipeline as per estimate - 113690m, laid - 60km , HTC - 680 FHTC - 0 Perambra PH Sn - AE
08 Jan 2024 Maruthonkara GP - pipeline as per estimate - 160945, laid - 69095, HTC - 0 FHTC - 0 Kavailumpara GP - pipeline as per estimate - 113690, laid - 59621, HTC - 664 FHTC - 0 Perambra PH Sn - AE
04 Jan 2024 Maruthonkara GP - pipeline as per estimate - 160945, laid - 68585, HTC - 0 FHTC - 0 Kavailumpara GP - pipeline as per estimate - 113690, laid - 59144, HTC - 600 FHTC - 0 Perambra PH Sn - AE
01 Jan 2024 Maruthonkara GP - pipeline as per estimate - 160945, laid - 67271, HTC - 0 FHTC - 0 Kavailumpara GP - pipeline as per estimate - 113690, laid - 58736, HTC - 560 FHTC - 0 Perambra PH Sn - AE
29 Dec 2023 Maruthonkara GP - pipeline as per estimate - 160945, laid - 67271, HTC - 0 FHTC - 0 Kavailumpara GP - pipeline as per estimate - 113690, laid - 58094, HTC - 514 FHTC - 0 Perambra PH Sn - AE
26 Dec 2023 90mm PVC laying work in progress .Total 65km pipe laid - Maruthonkara GP. 90mm PVC laying work in progress. Total 57km pipe laid ,Total House connection : 503 - Kavilumpara GP. Perambra PH Sn - AE
21 Dec 2023 90mm PVC laying work in progress .Total 63733m pipe laid - Maruthonkara GP. 90mm PVC laying work in progress. Total 56942m pipe laid ,Total House connection : 439 - Kavilumpara GP. Perambra PH Sn - AE
18 Dec 2023 90mm PVC laying work in progress .Total 60409m pipe laid - Maruthonkara GP. 90mm PVC laying work in progress. Total 56744m pipe laid ,Total House connection : 390 - Kavilumpara GP. Perambra PH Sn - AE
14 Dec 2023 90mm PVC laying work in progress .Total 60409m pipe laid - Maruthonkara GP. 90mm PVC laying work in progress. Total 56592m pipe laid ,Total House connection : 292 - Kavilumpara GP Perambra PH Sn - AE
11 Dec 2023 90mm ,110mm PVC laying work in progress .Total 54018m pipe laid - Maruthonkara GP. 90mm PVC laying work in progress. Total 55870m pipe laid ,Total House connection : 196 - Kavilumpara GP Perambra PH Sn - AE