23 May 2024 |
Maruthonkara GP - pipeline as per estimate - 160945m, laid - 94748m, HTC - 820 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1096 FHTC - 0. |
Perambra PH Sn - AE |
|
20 May 2024 |
Maruthonkara GP - pipeline as per estimate - 160945m, laid - 94320m, HTC - 820 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1096 FHTC - 0. |
Perambra PH Sn - AE |
|
16 May 2024 |
Maruthonkara GP - pipeline as per estimate - 160945m, laid - 94700m, HTC - 820 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1096 FHTC - 0. |
Perambra PH Sn - AE |
|
13 May 2024 |
Maruthonkara GP - pipeline as per estimate - 160945m, laid - 94700m, HTC - 820 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62822m , HTC - 1096 FHTC - 0. |
Perambra PH Sn - AE |
|
09 May 2024 |
Maruthonkara GP - pipeline as per estimate - 160945m, laid - 94158m, HTC - 820 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62051.3m , HTC - 1087 FHTC - 0. |
Perambra PH Sn - AE |
|
06 May 2024 |
Maruthonkara GP - pipeline as per estimate - 160945m, laid - 93948m, HTC - 820 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 62051.3m , HTC - 1087 FHTC - 0. |
Perambra PH Sn - AE |
|
02 May 2024 |
Maruthonkara GP - pipeline as per estimate - 160945m, laid - 93732m, HTC - 820 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 61865.3m , HTC - 1087 FHTC - 0. |
Perambra PH Sn - AE |
|
29 Apr 2024 |
Maruthonkara GP - pipeline as per estimate - 160945m, laid - 93560m, HTC - 815 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 66625.3m , HTC - 1087 FHTC - 0. |
Perambra PH Sn - AE |
|
25 Apr 2024 |
Maruthonkara GP - pipeline as per estimate - 160945m, laid - 93306m, HTC - 815 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 66625.3m , HTC - 1087 FHTC - 0. |
Perambra PH Sn - AE |
|
22 Apr 2024 |
Maruthonkara GP - pipeline as per estimate - 160945m, laid - 93198m, HTC - 805 FHTC - 0. Kavailumpara GP - pipeline as per estimate - 113690m, laid - 66625.3m , HTC - 1087 FHTC - 0. |
Perambra PH Sn - AE |
|