Status Date Overall Project Status Project Officer Contact
24 Sep 2021 Package 1-35MLD WTP- 22% of work completed. Sump cum filter house RCC work of base slab of filter unit completed . Plate settler clarifier and pump house plastering works in progress. Raw water pumping main- 700mm DI K9 pipe and 110/90/75mm PVC pipe distribution network laying work in progress. Package 2-Work order given to M/s Surya International and the agreement is executed. Malayil OHSR site handed over for the construction and soil investigation has been conducted by the Contractor. Package 3-Estimate returned from CEs office after correction and it will be submitted after ensuring the availability of land for OHSR at Kalarithara. For road restoration charge joint inspection with PWD completed in 90% of roads, joint inspection with PWD National highway completed on 6-8-2021. Package 4-Estimate submitted for approval. Joint inspection conducted at Kulikkampalam railway crossing on 30/7/2021.For road restoration charges PWD road details entered in ROW portal. Alappuzha KIIFB - AE 4
24 Aug 2021 Package 1-35MLD WTP- 22% of work completed. Sump cum filter house RCC work of base slab of filter unit completed . Plate settler clarifier and pump house plastering works in progress. Raw water pumping main- 700mm DI K9 pipe and 110/90/75mm PVC pipe distribution network laying work in progress. Package 2-Work order given to M/s Surya International and the agreement is executed. Malayil OHSR site handed over for the construction and soil investigation has been conducted by the Contractor. Package 3-Estimate returned from CEs office after correction and it will be submitted after ensuring the availability of land for OHSR at Kalarithara. For road restoration charge joint inspection with PWD completed in 90% of roads, joint inspection with PWD National highway completed on 6-8-2021. Package 4-Estimate submitted for approval. Joint inspection conducted at Kulikkampalam railway crossing on 30/7/2021.For road restoration charges PWD road details entered in ROW portal. Alappuzha KIIFB - AE 1
15 Jun 2021 PACKAGE 1-35MLD WTP- Sump cum filter house RCC work of wall and column in progress . Plate settler clarifier- H launder RCC work in progress. Pump house roof slab RCC work completed. Raw water pumping main- 700mm DI K9 pipe and 110/90/75mm PVC pipe distribution network laying work in progress. PACKAGE 2- Work order given to M/s Surya International and agreement is not executed. PACKAGE 3- Estimate returned from CEs office after correction and it will be submitted after ensuring the availability of land for OHSR at Kalarithara. For road restoration charge joint inspection with PWD in completed in 90% of roads, joint inspection with PWD National highway wing is pending. PACKAGE 4- Estimate Under preparation. Alappuzha KIIFB - AE 1
02 Jun 2021 Package I- 15% of total works completed. 35MLD WTP- Sump cum filter house RCC work of wall and column in progress . Plate settler clarifier- H launder RCC work in progress. Raw water pumping main - 700mm DI K9 pipe and 110/90/75mm PVC pipe distribution network laying work in progress. Package 2- Work tendered, quoted By Surya International and the agreement is not executed. Package 3-Estimate returned from CEs office after correction and it will be submitted after ensuring the availability of land for OHSR at Kalarithara. For road restoration charge joint inspection with PWD in completed in 90% of roads, joint inspection with PWD National highway wing is pending. Package 4-Estimate Under preparation, Estimate will submit to Circle office on 30/6/2021 Alappuzha KIIFB - AE 1
20 May 2021 Package I- Construction of 35MLD WTP and allied works 10% of the works completed. First unit with lamella plate settler clarifier, flash mixer RCC work almost completed. Second unit Sump cum filter house floor slab RCC work completed. Pump house plinth beam RCC work in progress. Intake well side temporary pump house erected. Raw water pumping main DI K9 700mm pipe 50% supplied and laying started. Package 2- Work tendered, quoted By Surya International - Changanassery road renovation work is in progress, the pipe line work in the Mulakkuzha panchayat in MC road of Chengannur package 3 is included in this package 2. Agreement not executed. Package 3- Estimate submitted to CE office for approval. Package 4- Estimate Under preparation, Estimate will submit to Circle office on 30/6/202 Alappuzha KIIFB - AE 1
19 Apr 2021 Package I- Construction of 35MLD WTP and allied works 10% of the works completed. First unit with lamella plate settler clarifier, flash mixer RCC work almost completed. Second unit Sump cum filter house floor slab RCC work completed. Pump house plinth beam RCC work in progress. Intake well side temporary pump house erected. Raw water pumping main DI K9 700mm pipe 50% supplied and laying will start after removing the road cutting ban during the election. Package 2- Work tendered, quoted By Surya International - Changanassery road renovation work is in progress, the pipe line work in the Mulakkuzha panchayat in MC road of Chengannur package 3 is included in this package 2. Agreement not executed. Package 3- Estimate submitted to CE office on 19/03/2021 and the estimate returned on 19/04/2021 for correction, will submit after correction. For road restoration charges the road details entered in ROW portal. Package 4- Estimate Under preparation, Estimate will submit to Circle office on 30/6/2021 Alappuzha KIIFB - AE 1
30 Mar 2021 package I -35MLD WTP plate settler clarifier RCC work of wall up to water carrying channel completed. PCC work of well cum filter house completed. For raw water pumping main 50% of 700mm DI K9 pipe supplied. Package 2-Work tendered, quoted By Surya International Tender documents submitted to head office for sanction Since Adoor - Changanassery road renovation work is in progress, the pipe line work in the Mulakkuzha panchayat in MC road of Chengannur package 3 is included in this package 2. Package 3-Estimate submitted to Circle office on 15/03/2021 except road restoration charges. Road restoration charges applied through ROW portal. Package 4-Estimate Under preparation, Estimate will submit to Circle office on 30/6/2021. Alappuzha KIIFB - AE 1
16 Mar 2021 For package I -35MLD WTP plate settler clarifier RCC work of wall up to water carrying channel completed. PCC work of well cum filter house completed. For raw water pumping main 50% of 700mm DI K9 pipe supplied. Alappuzha Project Dn AE4
04 Dec 2020 Package 1 , 35MLD WTP Clarifier work started. Alappuzha Project Dn AE4
04 Dec 2020 Package 2 tendered and will open on 14/12/2020 Alappuzha Project Dn AE4