| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Aug 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 17 Aug 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 16 Aug 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 13 Aug 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 12 Aug 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 09 Aug 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 08 Aug 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 07 Aug 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 06 Aug 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 05 Aug 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 |