| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Mar 2023 | Package I- Construction of 35 MLD WTP completed. Erection of 270 Hp raw water pump sets completed. For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13137m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 438m laid. 200 mm DI Pipe 446 m laid . Package III- Work tendered. The due date extended to 20.03.2023. Technical Bid opening on 21.03.2023.. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - Pipe laying- 110mm PVC pipe 5397m laid, 90mm PVC pipe 7129m, and 160mm PVC 1930m ,200mm DI 705m, 250mm DI 580m laid | Alappuzha KIIFB - AE 1 | |
| 21 Jan 2023 | Package I- Construction of 35 MLD WTP completed. Erection of 270 Hp raw water pump sets in progress. For electrical connection to RWPH and WTP fund requested to KIIFB for depositing in KSEB. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13101m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 438m laid. 200 mm DI Pipe 446 m laid . Package III- Tender work is in progress. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - Pipe laying- 110mm PVC pipe 3624m laid, 90mm PVC pipe 5292m, and 160mm PVC 1110m laid. | Alappuzha KIIFB - AE 1 | |
| 10 Jul 2022 | Package 1 - 35MLD WTP-Plate settler clarifier -Civil works completed. Mechanical work–Erection of SS plate for Plate settler completed. Erection of paddle wheel and motor drive in Flocculator and scrapper and motor drive in clarifier completed. Clearwater sump, pump house, filter house, chemical house, chlorine room- civil works completed. Filter house- Filter house pipe gallery DI pipe, fitting, valve erection completed clear water channel work completed. WWT- RCC work completed. OHSR civil work completed. Raw water pumping main- 700mm DI K9 pipe laying-2400m completed. 110/90/75mm PVC pipe distribution network laying work-2000m completed. Civil works of 750kVA/63kVA transformer room at Intake well site Pampa river basin RCC work completed. Retaining wall at RWPH site completed. 400kVA Transformer room at WTP site civil works completed. Aerator - works completed. Transformer 750/400/63kVA supplied at site. Raw water pumps and clear water pumps were supplied at the site and erection of clear water pumps completed. Construction of settling tank started. Package 2 - Concreting of raft foundation for OHSR is planned to be executed on 12/7/2022. Pipe laying- 110mm PVC pipe 9679m laid, 160mm PVC pipeline 12243m, and 90mm PVC pipe 6852m laid. 250 mm DI Pipe 288m laid. 200 mm DI Pipe 96 m laid (Total laid length=29158m). Package 3 - As per new directions, the detailed design of OHSRs is given to College of Engineering, Trivandrum for scrutiny. Road restoration estimates as per latest GO has been prepared. Package 4 - As per new directions, the detailed design of OHSRs is given to College of Engineering, Trivandrum for scrutiny. Road restoration estimates as per latest GO is under preparation. | Alappuzha KIIFB - AE 1 | |
| 30 May 2022 | Package I - 35MLD WTP-Plate settler clarifier -Civil works completed. Mechanical work–Erection of SS plate for Plate settler completed. Erection of paddle wheel and motor drive in Flocculator and scrapper and motor drive in clarifier completed. Clearwater sump, pump house ,filter house, chemical house, chlorine room- civil works completed. Filter house- Filter house pipe gallery DI pipe, fitting , valve erection completed clear water channel work in progress. WWT- RCC work completed. OHSR concreting completed. Raw water pumping main- 700mm DI K9 pipe laying-2000m completed. 110/90/75mm PVC pipe distribution network laying work-2000m completed. Civil works of 750kVA/63kVA transformer room at Intake well site Pampa river basin RCC work completed. Retaining wall at RWPH site completed. 400kVA Transformer room at WTP site civil works completed. For Aerator -RCC works completed. Transformer 750/400/63kVA supplied at site. Raw water pumps and clear water pumps were supplied at the site and erection of clear water pumps in progress. Temporary arrangement for pumping during the renovation work of existing pump house done at the site. Temporary bund constructed for the laying of leading pipe completed. Package II -PCC Work completed, Foundation reinforcement work is in progress OHSR at Malayil. Pipe laying- 110mm PVC pipe 9679m laid, 160mm PVC pipeline 11439m, and 90mm PVC pipe 6852m laid. 250 mm DI Pipe 126 m laid. 200 mm DI Pipe 96 m laid (Total laid length=28192 m) Package III -Estimate for all components except road restoration was ready for issuing TS. Now road restoration estimates as per latest GO completed. As per new directions, detailed design of OHSRs is under preparation. Package IV -Estimate for all components except road restoration was under scrutiny for issuing TS. Now as new directions, detailed design of OHSRs and Road restoration estimates as per the latest GO is under preparation. | Alappuzha KIIFB - AE 1 | |
| 18 Apr 2022 | Package I - 35MLD WTP-Plate settler clarifier -Civil works completed. Mechanical work started –Erection of SS plate for Plate settler started. Clearwater sump- civil works completed Filter house-RCC work up to roof slab and brickwork completed. Filter house pipe gallery works started. WWT- RCC work completed. OHSR concreting completed. Raw water pumping main- 700mm DI K9 pipe laying-1300m completed. 110/90/75mm PVC pipe distribution network laying work-1300m completed. Civil works of 750kVA/63kVA transformer room at Intake well site Pampa river basin floor slab are completed. Retaining wall at RWPH site completed. Chemical house /chlorine room RCC work completed and brickwork completed. 400kVA Transformer room at WTP site civil works completed. For Aerator -earthwork excavation was completed and RCC works started. Transformer 750/400/63kVA supplied at site. Raw water pumps and clear water pumps were supplied at the site. Temporary arrangement for pumping during the renovation work of existing pump house done at the site. Temporary bund constructed for the laying of leading pipe completed.700mm DI pipelaying work stopped due to heavy rain. Package II -Excavation work started at the construction of OHSR at Malayil. Pipe laying-110mm PVC pipe 7555m laid, 160mm PVC pipeline 9428m, and 90mm PVC pipe 5453m laid. 250 mm DI Pipe 126 m laid. 200 mm DI Pipe 96 m laid. Package III - Estimate for all components except road restoration was ready for issuing TS. Now as per new directions, detailed design of OHSRs and Road restoration estimates as per latest GO is under preparation. Package iV -Estimate for all components except road restoration was under scrutiny for issuing TS. Now as new directions, detailed design of OHSRs and Road restoration estimates as per latest GO is under preparation. | Alappuzha KIIFB - EE | |
| 16 Mar 2022 | Package 1- Construction of 35 MLD WTP and allied works- 52% of work completed. Sump, filter, Wash water tank, Plate settler, pump house, Chemical house are completed. Raw water pumping main- 700mm DI K9 pipe and 110/90/75mm PVC pipe distribution network laying work in progress. Piling work for transformer room and construction of retaining wall at Raw water intake are completed. Transformer room construction completed. Package 2-OHSR construction site at Malayil cleared for excavation and excavation started. Pipe laying-110mm PVC pipe 6793m laid , 160mm PVC pipe line 8435m and 90mm PVC pipe 5192m laid. The signed GAD is submitted to railway for getting sanction for push through work at RUB Chengannur. Package 3- Estimate for ‘construction of OHSRs at Parachanda, Pennukkara and Kalarithara ( for Mulakkuzha, Venmony and Ala panchayats) and supply and laying of distribution systems in Mulakkuzha and Venmony panchayats’ is ready for issuing TS. The land for construction of OHSR at Kalarithara obtained. PWD road details entered in ROW portal and joint inspection with PWD completed. Detailed road restoration estimates not obtained. Package 4- Estimate for ‘construction of OHSRs at Thuruthimel, Pandanad and Puliyoor ( for Cheriyanad Pandanad, Puliyoor and Budhanoor panchayats) and supply and laying of distribution systems in Ala, Pandanad, Puliyoor and Budhanoor panchayats’ is under editin. PWD road details entered in ROW portal and joint inspection with PWD completed and requested for detailed road restoration estimate. Detailed road restoration estimates not obtained. Joint inspection conducted at Kulikkampalam railway crossing and centage charge remitted. | Alappuzha KIIFB - AE 1 | |
| 02 Feb 2022 | Package 1- Construction of 35 MLD WTP and allied works- 48% of work completed. Sump, filter , Wash water tank, Plate settler, pump house, Chemical house are completed. Raw water pumping main- 700mm DI K9 pipe and 110/90/75mm PVC pipe distribution network laying work in progress. Piling work for transformer room and construction of retaining wall at Raw water intake are completed. Transformer room columns raised to roof slab. Shuttering and reinforcement work in progress. Package 2-OHSR construction site at Malayil cleared for excavation. Pipe laying-110mm PVC pipe 2468m laid , 160mm PVC pipe line 2910m and 90mm PVC pipe 1848m laid. The signed GAD is submitted to railway for getting sanction for push through work at RUB Chengannur. Package 3- Estimate for ‘construction of OHSRs at Parachanda, Pennukkara and Kalarithara ( for Mulakkuzha, Venmony and Ala panchayats) and supply and laying of distribution systems in Mulakkuzha and Venmony panchayats’ is ready for issuing TS. The land for construction of OHSR at Kalarithara obtained. PWD road details entered in ROW portal and joint inspection with PWD completed. Detailed road restoration estimates not obtained. Package 4- Estimate for ‘construction of OHSRs at Thuruthimel, Pandanad and Puliyoor ( for Cheriyanad Pandanad, Puliyoor and Budhanoor panchayats) and supply and laying of distribution systems in Ala, Pandanad, Puliyoor and Budhanoor panchayats’ is under editing as per the comments from CE’s office. PWD road details entered in ROW portal and joint inspection with PWD completed and requested for detailed road restoration estimate. Detailed road restoration estimates not obtained. Joint inspection conducted at Kulikkampalam railway crossing and centage charge remitted. | Alappuzha KIIFB - EE | |
| 09 Jan 2022 | Package 1- Construction of 35 MLD WTP and allied works- 44% of work completed. Sump, filter , Wash water tank, Plate settler, pump house, Chemical house are completed. Raw water pumping main- 700mm DI K9 pipe and 110/90/75mm PVC pipe distribution network laying work in progress. Piling work for transformer room and construction of retaining wall at Raw water intake are completed. Package 2-The pipe laying work started at Chengannur Municipality by M/s Surya International. The approved structural drawing foe 15 LL capacity OHSR at Malayil is submitted by the contractor and site clearing works started. The signed GAD is submitted to railway for getting sanction for push through work at RUB Chengannur. Package 3- Estimate for ‘construction of OHSRs at Parachanda, Pennukkara and Kalarithara ( for Mulakkuzha, Venmony and Ala panchayats) and supply and laying of distribution systems in Mulakkuzha and Venmony panchayats’ is ready for issuing TS. The land for construction of OHSR at Kalarithara obtained. PWD road details entered in ROW portal and joint inspection with PWD completed and requested for detailed road restoration estimate. Package 4- Estimate for ‘construction of OHSRs at Thuruthimel, Pandanad and Puliyoor ( for Cheriyanad Pandanad, Puliyoor and Budhanoor panchayats) and supply and laying of distribution systems in Ala, Pandanad, Puliyoor and Budhanoor panchayats’ is under editing as per the comments from CE’s office. PWD road details entered in ROW portal and joint inspection with PWD completed and requested for detailed road restoration estimate. Joint inspection conducted at Kulikkampalam railway crossing and centage charge remitted | Alappuzha KIIFB - AE 1 | |
| 08 Jan 2022 | Package 1- Construction of 35 MLD WTP and allied works- 44% of work completed. Sump, filter , Wash water tank, Plate settler, pump house, Chemical house are completed. Raw water pumping main- 700mm DI K9 pipe and 110/90/75mm PVC pipe distribution network laying work in progress. Piling work for transformer room and construction of retaining wall at Raw water intake are completed. Package 2-The pipe laying work started at Chengannur Municipality by M/s Surya International. The approved structural drawing foe 15 LL capacity OHSR at Malayil is submitted by the contractor and site clearing works started. The signed GAD is submitted to railway for getting sanction for push through work at RUB Chengannur. Package 3- Estimate for ‘construction of OHSRs at Parachanda, Pennukkara and Kalarithara ( for Mulakkuzha, Venmony and Ala panchayats) and supply and laying of distribution systems in Mulakkuzha and Venmony panchayats’ after incorporating corrections suggested by CE’s office is submitted for issuing TS. The land for construction of OHSR at Kalarithara obtained. PWD road details entered in ROW portal and joint inspection with PWD completed and requested for detailed road restoration estimate. Package 4- Estimate for ‘construction of OHSRs at Thuruthimel, Pandanad and Puliyoor ( for Cheriyanad Pandanad, Puliyoor and Budhanoor panchayats) and supply and laying of distribution systems in Ala, Pandanad, Puliyoor and Budhanoor panchayats’ is submitted to CE’s office. PWD road details entered in ROW portal and joint inspection with PWD completed and requested for detailed road restoration estimate. Joint inspection conducted at Kulikkampalam railway crossing and centage charge remitted | Alappuzha KIIFB - AE 1 | |
| 28 Dec 2021 | Package 1- Construction of 35 MLD WTP and allied works- 40% of work completed. Sump, filter , Wash water tank, Plate settler, pump house, Chemical house are completed. Raw water pumping main- 700mm DI K9 pipe and 110/90/75mm PVC pipe distribution network laying work in progress. Piling work for transformer room and construction of retaining wall at Raw water intake are completed. Package 2-The pipe laying work started at Chengannur Municipality by M/s Surya International. The approved structural drawing foe 15 LL capacity OHSR at Malayil is submitted by the contractor. The signed GAD is submitted to railway for getting sanction for push through work at RUB Chengannur. Package 3- Estimate for ‘construction of OHSRs at Parachanda, Pennukkara and Kalarithara ( for Mulakkuzha, Venmony and Ala panchayats) and supply and laying of distribution systems in Mulakkuzha and Venmony panchayats’ after incorporating corrections suggested by CE’s office is submitted for issuing TS. The land for construction of OHSR at Kalarithara obtained. PWD road details entered in ROW portal and joint inspection with PWD completed and requested for detailed road restoration estimate. Package 4- Estimate for ‘construction of OHSRs at Thuruthimel, Pandanad and Puliyoor ( for Cheriyanad Pandanad, Puliyoor and Budhanoor panchayats) and supply and laying of distribution systems in Ala, Pandanad, Puliyoor and Budhanoor panchayats’ is submitted to CE’s office. PWD road details entered in ROW portal and joint inspection with PWD completed and requested for detailed road restoration estimate. Joint inspection conducted at Kulikkampalam railway crossing and centage charge remitted. | Kottayam Project Dn AEE2 KIFFB |