Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Nov 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 97% work is Completed, and Package 7- 94% work completed. |
Cherpu AE |
|
20 Nov 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 97% work is Completed, and Package 7- 92% work completed. |
Cherpu AE |
|
13 Nov 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 97% work is Completed, and Package 7- 92% work completed. |
Cherpu AE |
|
06 Nov 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 97% work is Completed, and Package 7- 92% work completed. |
Cherpu AE |
|
03 Nov 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 97% work is Completed, and Package 7- 92% work completed. |
Cherpu AE |
|
31 Oct 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 95% work is Completed, and Package 7- 90% work completed. |
Cherpu AE |
|
27 Oct 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 95% work is Completed, and Package 7- 90% work completed. |
Cherpu AE |
|
23 Oct 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 95% work is Completed, and Package 7- 90% work completed. |
Cherpu AE |
|
20 Oct 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 95% work is Completed, and Package 7- 90% work completed. |
Cherpu AE |
|
16 Oct 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 95% work is Completed, and Package 7- 90% work completed. |
Cherpu AE |
|