Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Nov 2023 Package 1,2,3,4,6 are Completed, Package 6- 97% work is Completed, and Package 7- 94% work completed. Cherpu AE
20 Nov 2023 Package 1,2,3,4,6 are Completed, Package 6- 97% work is Completed, and Package 7- 92% work completed. Cherpu AE
13 Nov 2023 Package 1,2,3,4,6 are Completed, Package 6- 97% work is Completed, and Package 7- 92% work completed. Cherpu AE
06 Nov 2023 Package 1,2,3,4,6 are Completed, Package 6- 97% work is Completed, and Package 7- 92% work completed. Cherpu AE
03 Nov 2023 Package 1,2,3,4,6 are Completed, Package 6- 97% work is Completed, and Package 7- 92% work completed. Cherpu AE
31 Oct 2023 Package 1,2,3,4,6 are Completed, Package 6- 95% work is Completed, and Package 7- 90% work completed. Cherpu AE
27 Oct 2023 Package 1,2,3,4,6 are Completed, Package 6- 95% work is Completed, and Package 7- 90% work completed. Cherpu AE
23 Oct 2023 Package 1,2,3,4,6 are Completed, Package 6- 95% work is Completed, and Package 7- 90% work completed. Cherpu AE
20 Oct 2023 Package 1,2,3,4,6 are Completed, Package 6- 95% work is Completed, and Package 7- 90% work completed. Cherpu AE
16 Oct 2023 Package 1,2,3,4,6 are Completed, Package 6- 95% work is Completed, and Package 7- 90% work completed. Cherpu AE