Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Jan 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed. |
Cherpu AE |
|
19 Jan 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed. |
Cherpu AE |
|
16 Jan 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed. |
Cherpu AE |
|
13 Jan 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed. |
Cherpu AE |
|
10 Jan 2024 |
Package 1,2,3,4,5 are Completed, Package 6- work Completed, and Package 7- 94% work is completed. |
Cherpu AE |
|
18 Jan 2024 |
Package 1,2,3,4,5 are Completed, Package 6- 97% work is Completed, and Package 7- 94% work is completed. |
Cherpu AE |
|
15 Jan 2024 |
Package 1,2,3,4,5 are Completed, Package 6- 97% work is Completed, and Package 7- 94% work is completed. |
Cherpu AE |
|
11 Jan 2024 |
Package 1,2,3,4,5 are Completed, Package 6- 97% work is Completed, and Package 7- 94% work is completed. |
Cherpu AE |
|
08 Jan 2024 |
Package 1,2,3,4,5 are Completed, Package 6- 97% work is Completed, and Package 7- 94% work is completed. |
Cherpu AE |
|
03 Jan 2024 |
Package 1,2,3,4,5 are Completed, Package 6- 97% work is Completed, and Package 7- 94% work completed. |
Cherpu AE |
|