Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Mar 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed, Package8:-28%completed. |
Cherpu AE |
|
22 Mar 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed, Package8:-28%completed. |
Cherpu AE |
|
16 Mar 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed, Package 8:Pipe laying work is in Progress-28%completed. |
Cherpu AE |
|
11 Mar 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed, Package 8:Pipe laying work is in Progress-28%completed. |
Cherpu AE |
|
08 Mar 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed, Package 8:Pipe laying work is in Progress-28%completed. |
Cherpu AE |
|
05 Mar 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed, Package 8:Pipe laying work is in Progress-21%completed. |
Cherpu AE |
|
02 Mar 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed, Package 8:Pipe laying work is in Progress-15%completed. |
Cherpu AE |
|
28 Feb 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed, Package 8:Work started-Pipe laying work is in Progress. |
Cherpu AE |
|
26 Feb 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed, Package 8:Work started-Pipe laying work is in Progress. |
Cherpu AE |
|
22 Feb 2024 |
Package 1,2,3,4,5,6 are Completed and Package 7- 94% work is completed, Package 8:Work started-Pipe laying work is in Progress. |
Cherpu AE |
|