| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Sep 2020 | The work commenced during November 2018. On executing the work as per the beneficiary list submitted by the corporation authorities, it was seen that the connections are mostly on concrete or tar road as most of the earthen roads are got tarred or concreted and also an average length of about 15mts needed for the satisfactory completion of the work. Hence revised estimate submitted. | Kollam PH Dn EE | |
| 11 Sep 2020 | The work commenced during November 2018. On executing the work as per the beneficiary list submitted by the corporation authorities, it was seen that the connections are mostly on concrete or tar road | Kollam PH Dn EE |