| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 08 Mar 2021 | Awaiting Revised TS | Kollam PH Dn EE | |
| 25 Feb 2021 | Revised AS approved by GoK dt.24.2.2021 | Kollam PH Dn EE | |
| 23 Feb 2021 | Awaiting GO for revised AS. | Kollam PH Dn EE | |
| 17 Feb 2021 | Awaiting GO for revised AS. | Kollam PH Dn EE | |
| 12 Feb 2021 | Awaiting GO for revised AS. | Kollam PH Dn EE | |
| 05 Feb 2021 | SHPSC approved the proposal for revised AS.Awaiting G.O. | Kollam PH Dn EE | |
| 05 Feb 2021 | Revised TS to be sanctioned | Kollam PH Dn EE | |
| 11 Jan 2021 | AS for revised estimate sanctioned. Submitted for revised TS | Kollam PH Dn EE | |
| 15 Dec 2020 | While preparing estimate on 2016,beneficiary list has not received and estimate prepared assuming that most connections are on earthern road and an average length of service line with 8m. But after receiving the beneficiary list on 10/2018,work started on 11/2018 and on execution it was seen that the connections are mostly on concrete/tar road with an average length of about 20m. | Kollam PH Dn EE | |
| 11 Nov 2020 | Out of 10000 water connections, 8324 Nos of water connections given. As per the demand of Kollam corporation during the core committee meeting held on 12.06.2020, additional 1676 nos of connections from the list of consumers in the 2nd phase of AMRUT SAAP year 16-17 is incorporated and submitted to the secretary Kollam corporation for an amount of Rs.9.2752 Crores for getting revised A.S including tender excess of 5.64%. Placed in 25th SHPSC. Deferred. | Kollam PH Dn EE |