| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Apr 2021 | 8494 connections are given.Increased spread of covid 19 pandamic and related shortage of labour is slowing down the pace of activitiesthan expected. | Kollam PH Dn EE | |
| 30 Apr 2021 | 8459 connections are given. | Kollam PH Dn EE | |
| 27 Apr 2021 | 8434 connections are given | Kollam PH Dn EE | |
| 26 Apr 2021 | 8409 connections given. | Kollam PH Dn EE | |
| 23 Apr 2021 | 8397 connections given. | Kollam PH Dn EE | |
| 21 Apr 2021 | 8377 connection completed | Kollam PH Dn EE | |
| 16 Apr 2021 | work restarted | Kollam PH Dn EE | |
| 08 Apr 2021 | Additional agreement executed on 23/03/2021 for providing balanced connection as per revised TS | Kollam PH Dn EE | |
| 30 Mar 2021 | Additional agreement to be executed for providing balanced connection as per revised TS | Kollam PH Dn EE | |
| 17 Mar 2021 | Revised TS sanctioned on 16/03/2021 for 878 Lakhs | Kollam PH Dn EE |