| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Sep 2021 | work completed | Kollam PH Dn EE | |
| 16 Aug 2021 | work completed | Kollam PH Dn EE | |
| 11 Aug 2021 | 10000 connections given and work completed | Kollam PH Dn EE | |
| 10 Aug 2021 | 9758 connections are given | Kollam PH Dn EE | |
| 08 Aug 2021 | 9658 connections are given | Kollam PH Dn EE | |
| 06 Aug 2021 | 9578 connections are given | Kollam PH Dn EE | |
| 05 Aug 2021 | 9458 connections are given | Kollam PH Dn EE | |
| 03 Aug 2021 | 9438 connections are given | Kollam PH Dn EE | |
| 02 Aug 2021 | 9218 connections are given | Kollam PH Dn EE | |
| 30 Jul 2021 | 9218 connections are given | Kollam PH Dn EE |