| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Jun 2021 | 8709 connections are given. | Kollam PH Dn EE | |
| 28 Jun 2021 | 8684 connections are given | Kollam PH Dn EE | |
| 24 Jun 2021 | 8663 connections are given. | Kollam PH Dn EE | |
| 23 Jun 2021 | 8623 connections are given | Kollam PH Dn EE | |
| 22 Jun 2021 | 8623 connections are given | Kollam PH Dn EE | |
| 21 Jun 2021 | 8604 connections are given. | Kollam PH Dn EE | |
| 18 Jun 2021 | 8604 connections are given. | Kollam PH Dn EE | |
| 17 Jun 2021 | 8584connections are given. | Kollam PH Dn EE | |
| 15 Jun 2021 | No progress of work due to increased spread of covid 19 | Kollam PH Dn EE | |
| 14 Jun 2021 | No progress of work due to increased spread of covid 19. | Kollam PH Dn EE |