Status Date |
Overall Project Status |
Project Officer |
Contact |
27 Sep 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.82 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4143.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (591 nos) & HTC (580 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed.
|
Palakkad Proj AE 3 |
|
26 Sep 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.77 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4095.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (551 nos) & HTC (630 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. |
Palakkad Proj AE 3 |
|
25 Sep 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.48 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 3801.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (551 nos) & HTC (630 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. |
Palakkad Proj AE 3 |
|
23 Sep 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.48 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 3801.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (551 nos) & HTC (630 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. |
Palakkad Proj AE 3 |
|
21 Sep 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.48 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 3801.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (551 nos) & HTC (630 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. |
Palakkad Proj AE 3 |
|
20 Sep 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.38 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 3705.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (470 nos) & HTC (701 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed.
|
Palakkad Proj AE 3 |
|
19 Sep 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.38 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 3705.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (470 nos) & HTC (701 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed.
|
Palakkad Proj AE 3 |
|
18 Sep 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.24 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 3561.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (745 nos) & HTC ( 426 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. |
Palakkad Project Dn EE |
|
15 Sep 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.08 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 3407.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (745 nos) & HTC ( 426 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. |
Palakkad Proj AE 3 |
|
14 Sep 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.08 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 3407.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (745 nos) & HTC ( 426 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. |
Palakkad Proj AE 3 |
|