Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Nov 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.73 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:4871.2 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC- 1064 & HTC - 130/2623 completed.PWD road cutting permission (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) issued. Palakkad Proj AE 3
17 Nov 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.65 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4703.2 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC- 1064 & HTC - 130/2623 completed.PWD road cutting permission (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) issued. Palakkad Proj AE 3
16 Nov 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.65 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4703.2 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC- 1064 & HTC - 130/2623 completed.PWD road cutting permission (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) issued. Palakkad Proj AE 3
17 Nov 2023 52.34 Km (including GI 1500 m)out of 63 km completed . Remaining HDPE ,DI & GI pipe laying work , interconnection & gap filling work progress, Road restoration work on going, FHTC -1245 nos & HTC- 636/4635 completed. PWD road cutting permission(Kanjirapuzha - Mundakkunnu- ambazhakode road) issued. Palakkad Proj AE 3
16 Nov 2023 52.34 Km (including GI 1500 m)out of 63 km completed . Remaining HDPE ,DI & GI pipe laying work , interconnection & gap filling work progress, Road restoration work on going, FHTC -1245 nos & HTC- 636/4635 completed. PWD road cutting permission(Kanjirapuzha - Mundakkunnu- ambazhakode road) issued. Palakkad Proj AE 3
15 Nov 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.56 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4703.2 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC- 1064& HTC - 130/2623 completed.PWD road cutting permission (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) issued. Palakkad Proj AE 3
14 Nov 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.56 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4703.2 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC- 1058 & HTC - 134/2623 completed.PWD road cutting permission (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) issued. Palakkad Proj AE 3
13 Nov 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.56 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4703.2 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC- 1058 & HTC - 134/2623 completed.PWD road cutting permission (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) issued. Palakkad Proj AE 3
10 Nov 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.55 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4690.2 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC- 1058 & HTC - 134/2623 completed.PWD road cutting permission (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) issued. Palakkad Proj AE 3
08 Nov 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.47 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4606.2 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC- 1058 & HTC - 134/2623 completed.PWD road cutting permission (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) issued. Palakkad Proj AE 3