Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Jun 2024 | 49.172 km completed.GI 5.135/5.826 km completed, All PWD road work completed. House connection 1432 nos , Geo tagged -1389 nos completed & FHTC - 1339 | Palakkad Proj AE 3 | |
26 Jun 2024 | 49.172 km completed.GI 5.135/5.826 km completed, All PWD road work completed. House connection 1432 nos , Geo tagged -1389 nos completed & FHTC - 1339 | Palakkad Proj AE 3 | |
25 Jun 2024 | 49.17 km completed.GI 5.135/5.826 km completed, All PWD road work completed. House connection 1430 nos , Geo tagged -1387 nos completed & FHTC - 1334. | Palakkad Proj AE 3 | |
22 Jun 2024 | 49.17 km completed.GI 5.135/5.826 km completed, All PWD road work completed. House connection 1428 nos , Geo tagged -1381 nos completed & FHTC - 1334. | Palakkad Proj AE 3 | |
21 Jun 2024 | 49.17 km completed.GI 5.135/5.826 km completed, All PWD road work completed. House connection 1428 nos , Geo tagged -1381 nos completed & FHTC - 1334. | Palakkad Proj AE 3 | |
17 Jun 2024 | 49.17 km completed.GI 5.135/5.826 km completed, All PWD road work completed. House connection 1425 nos , Geo tagged -1377 nos completed & FHTC - 1330. | Palakkad Proj AE 3 | |
13 Jun 2024 | 49.17 km completed.GI 5.135/5.826 km completed, All PWD road work completed. House connection 1423 nos , Geo tagged -1372 nos completed & FHTC - 1330. | Palakkad Proj AE 3 | |
07 Jun 2024 | 49.17 km completed.GI 5.135/5.826 km completed, All PWD road work completed. House connection 1421 nos , Geo tagged -1359 nos completed & FHTC - 1321. | Palakkad Proj AE 3 | |
31 May 2024 | 49.17 km completed.GI 5.135/5.826 km completed, All PWD road work completed. House connection 1409 nos , Geo tagged -1355 nos completed & FHTC - 1321. | Palakkad Project Dn EE | |
27 May 2024 | 49.17/65.2 km completed.GI 5.135/5.826 km completed, All PWD road work completed. House connection 1409 nos , Geo tagged -1355 nos completed & FHTC - 1321. | Palakkad Proj AE 3 |