Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Aug 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 46.00 km laid (including 250mm DI Pipe - 39556.8 m, Total GI pipe lied: 3104.8 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (367 nos) & HTC ( 783 no's) work progressing.PWD road cutting permission issued (Viyakkurissi to Vazhempuram,Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). |
Palakkad Proj AE 3 |
|
24 Aug 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 45.00 km laid (including 250mm DI Pipe - 4115.5 m, Total GI pipe lied: 3685 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (367 nos) & HTC ( 775 no's) work progressing.PWD road cutting permission issued (Viyakkurissi to Vazhempuram,Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). |
Palakkad Proj AE 3 |
|
23 Aug 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 45.00 km laid (including 250mm DI Pipe - 4115.5 m, Total GI pipe lied: 3685 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (367 nos) & HTC ( 775 no's) work progressing.PWD road cutting permission issued (Viyakkurissi to Vazhempuram,Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). |
Palakkad Proj AE 3 |
|
22 Aug 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 45.00 km laid (including 250mm DI Pipe - 4115.5 m, Total GI pipe lied: 3685 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (367 nos) & HTC ( 775 no's) work progressing.PWD road cutting permission issued (Viyakkurissi to Vazhempuram,Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). |
Palakkad Proj AE 3 |
|
21 Aug 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 45.00 km laid (including 250mm DI Pipe - 4115.5 m, Total GI pipe lied: 3685 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (341 nos) & HTC ( 801 no's) work progressing.PWD road cutting permission issued (Viyakkurissi to Vazhempuram,Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) & work not started due to monsoon ban. |
Palakkad Proj AE 3 |
|
19 Aug 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 44.50 km laid (including 250mm DI Pipe - 4115.5 m, Total GI pipe lied: 3685 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (341 nos) & HTC ( 801 no's) work progressing.PWD road cutting permission issued (Viyakkurissi to Vazhempuram,Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) & work not started due to monsoon ban. |
Palakkad Proj AE 3 |
|
18 Aug 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 44.50 km laid (including 250mm DI Pipe - 4115.5 m, Total GI pipe lied: 3685 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (341 nos) & HTC ( 801 no's) work progressing.PWD road cutting permission issued (Viyakkurissi to Vazhempuram,Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) & work not started due to monsoon ban. |
Palakkad Proj AE 3 |
|
17 Aug 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 44.50 km laid (including 250mm DI Pipe - 4115.5 m, Total GI pipe lied: 3685 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (341 nos) & HTC ( 801 no's) work progressing.PWD road cutting permission issued (Viyakkurissi to Vazhempuram,Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) & work not started due to monsoon ban. |
Palakkad Proj AE 3 |
|
16 Aug 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 44.50 km laid (including 250mm DI Pipe - 4115.5 m, Total GI pipe lied: 3685 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (341 nos) & HTC ( 801 no's) work progressing.PWD road cutting permission issued (Viyakkurissi to Vazhempuram,Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) & work not started due to monsoon ban. |
Palakkad Proj AE 3 |
|
14 Aug 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 44.50 km laid (including 250mm DI Pipe - 4115.5 m, Total GI pipe lied: 3685 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (341 nos) & HTC ( 801 no's) work progressing.PWD road cutting permission issued (Viyakkurissi to Vazhempuram,Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) & work not started due to monsoon ban. |
Palakkad Proj AE 3 |
|