Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Sep 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.05 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 3377.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (745 nos) & HTC ( 426 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. Palakkad Proj AE 3
12 Sep 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 46.98 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 3305.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (746 nos) & HTC ( 415 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. Palakkad Proj AE 3
11 Sep 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 46.87 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 3197.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (746 nos) & HTC ( 415 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. Palakkad Proj AE 3
08 Sep 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 46.78 km laid (including 250mm DI Pipe - 39556.8 m, Total GI pipe lied: 3104.8 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (415 nos) & HTC ( 735 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. Palakkad Proj AE 3
07 Sep 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 46.78 km laid (including 250mm DI Pipe - 39556.8 m, Total GI pipe lied: 3104.8 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (415 nos) & HTC ( 735 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. Palakkad Proj AE 3
05 Sep 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 46.78 km laid (including 250mm DI Pipe - 39556.8 m, Total GI pipe lied: 3104.8 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (415 nos) & HTC ( 735 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. Palakkad Proj AE 3
04 Sep 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 46.78 km laid (including 250mm DI Pipe - 39556.8 m, Total GI pipe lied: 3104.8 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (367 nos) & HTC ( 783 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. Palakkad Proj AE 3
02 Sep 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 46.78 km laid (including 250mm DI Pipe - 39556.8 m, Total GI pipe lied: 3104.8 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (367 nos) & HTC ( 783 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. Palakkad Proj AE 3
01 Sep 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 46.00 km laid (including 250mm DI Pipe - 39556.8 m, Total GI pipe lied: 3104.8 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (367 nos) & HTC ( 783 no's) work progressing.PWD road cutting permission issued (Viyakkurissi to Vazhempuram,Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). Palakkad Proj AE 3
26 Aug 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 46.00 km laid (including 250mm DI Pipe - 39556.8 m, Total GI pipe lied: 3104.8 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (367 nos) & HTC ( 783 no's) work progressing.PWD road cutting permission issued (Viyakkurissi to Vazhempuram,Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). Palakkad Proj AE 3