Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Oct 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.29 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4429.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC- 969 & HTC - 213/2623 completed.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). Palakkad Proj AE 3
10 Oct 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.27 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC-856 & HTC -326/2623 completed.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). Palakkad Proj AE 3
09 Oct 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.27 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC-840 & HTC -342/2623 completed.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). Palakkad Proj AE 3
07 Oct 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.16 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC-730 & HTC -452/2623 completed.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). Palakkad Proj AE 3
06 Oct 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.16 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC-730 & HTC -452/2623 completed.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). Palakkad Proj AE 3
05 Oct 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.08 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC -620 & HTC-561/2623 completed.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. Palakkad Proj AE 3
04 Oct 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.08 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (620 nos) & HTC (553 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. Palakkad Proj AE 3
03 Oct 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.08 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (620 nos) & HTC (553 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. Palakkad Proj AE 3
30 Sep 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.96 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4287.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (591 nos) & HTC (580 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. Palakkad Proj AE 3
29 Sep 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.96 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4287.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (591 nos) & HTC (580 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. Palakkad Proj AE 3