Status Date |
Overall Project Status |
Project Officer |
Contact |
11 Oct 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.29 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4429.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC- 969 & HTC - 213/2623 completed.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road).
|
Palakkad Proj AE 3 |
|
10 Oct 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.27 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC-856 & HTC -326/2623 completed.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road).
|
Palakkad Proj AE 3 |
|
09 Oct 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.27 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC-840 & HTC -342/2623 completed.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). |
Palakkad Proj AE 3 |
|
07 Oct 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.16 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC-730 & HTC -452/2623 completed.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). |
Palakkad Proj AE 3 |
|
06 Oct 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.16 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC-730 & HTC -452/2623 completed.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road). |
Palakkad Proj AE 3 |
|
05 Oct 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.08 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC -620 & HTC-561/2623 completed.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed.
|
Palakkad Proj AE 3 |
|
04 Oct 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.08 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (620 nos) & HTC (553 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed.
|
Palakkad Proj AE 3 |
|
03 Oct 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 48.08 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4401.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (620 nos) & HTC (553 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed.
|
Palakkad Proj AE 3 |
|
30 Sep 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.96 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4287.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (591 nos) & HTC (580 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed. |
Palakkad Proj AE 3 |
|
29 Sep 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 47.96 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied: 4287.4 m).Remaining HDPE & GI pipe line , road restoration work & interconnection progressing, FHTC (591 nos) & HTC (580 no's) work progressing.PWD road cutting permission issued (Perubaderi pullissery,Pallippadi Karakkurissi road & Edaikkal to Koottilakkadav road) ,PWD road crossing(Viyakkurissi to Vazhempuram road) work completed.
|
Palakkad Proj AE 3 |
|