Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Jan 2024 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5012.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1150 & HTC - 80/2623 completed. Palakkad Proj AE 3
04 Jan 2024 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5012.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1150 & HTC - 80/2623 completed. Palakkad Proj AE 3
03 Jan 2024 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed. Palakkad Proj AE 3
01 Jan 2024 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed Palakkad Proj AE 3
30 Dec 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed Palakkad Proj AE 3
30 Dec 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed Palakkad Proj AE 3
04 Jan 2024 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed. Palakkad Proj AE 3
29 Dec 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed. Palakkad Proj AE 3
28 Dec 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed. Palakkad Proj AE 3
27 Dec 2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed. Palakkad Proj AE 3