Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Jan 2024 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5012.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1150 & HTC - 80/2623 completed. |
Palakkad Proj AE 3 |
|
04 Jan 2024 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5012.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1150 & HTC - 80/2623 completed. |
Palakkad Proj AE 3 |
|
03 Jan 2024 |
2023 Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed. |
Palakkad Proj AE 3 |
|
01 Jan 2024 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed |
Palakkad Proj AE 3 |
|
30 Dec 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed |
Palakkad Proj AE 3 |
|
30 Dec 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed |
Palakkad Proj AE 3 |
|
04 Jan 2024 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed. |
Palakkad Proj AE 3 |
|
29 Dec 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed.
|
Palakkad Proj AE 3 |
|
28 Dec 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed.
|
Palakkad Proj AE 3 |
|
27 Dec 2023 |
Supplied pipe -65.2 km , GI pipe supplied - 5.826 km , 49.04 km laid (including 250mm DI Pipe - 4123 m, Total GI pipe lied:5009.95 m).Remaining HDPE & GI pipe line , All PWD road work completed. FHTC- 1124 & HTC - 103/2623 completed.
|
Palakkad Proj AE 3 |
|