Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Oct 2021 Pipe supply is pending due to non conducting test by CIPET Alappuzha Project Dn AE4
28 Sep 2021 Work inaugurated by Hon'ble Minister for Fisheries and Culture Sri. Saji Cherian on 26-09-2021 by providing a FHTC in ward 11 of Mannar Panchayath Alappuzha Project Dn AE4
25 Sep 2021 FHTC is given for inauguration by Ho'ble Minister for Fisheries Sri. Saji Cherian on 26-09-2021 Alappuzha Project Dn AE4
22 Sep 2021 Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far. Marking of existing lines in the design drawing is progressing. Work inauguration planned to be on 26/09/2021 Alappuzha Project Dn AE4
20 Sep 2021 Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far. Marking of existing lines in the design drawing is progressing Alappuzha Project Dn AE4
18 Sep 2021 Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far. Marking of existing lines in the design drawing is progressing Alappuzha Project Dn AE4
15 Sep 2021 Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far. Marking of existing lines in the design drawing is progressing Alappuzha Project Dn AE4
14 Sep 2021 Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far. Marking of existing lines in the design drawing is progressing Alappuzha Project Dn AE4
13 Sep 2021 Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far. Marking of existing lines in the design drawing is progressing Alappuzha Project Dn AE4
08 Sep 2021 Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far Alappuzha Project Dn AE4