Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Oct 2021 | Pipe supply is pending due to non conducting test by CIPET | Alappuzha Project Dn AE4 | |
28 Sep 2021 | Work inaugurated by Hon'ble Minister for Fisheries and Culture Sri. Saji Cherian on 26-09-2021 by providing a FHTC in ward 11 of Mannar Panchayath | Alappuzha Project Dn AE4 | |
25 Sep 2021 | FHTC is given for inauguration by Ho'ble Minister for Fisheries Sri. Saji Cherian on 26-09-2021 | Alappuzha Project Dn AE4 | |
22 Sep 2021 | Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far. Marking of existing lines in the design drawing is progressing. Work inauguration planned to be on 26/09/2021 | Alappuzha Project Dn AE4 | |
20 Sep 2021 | Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far. Marking of existing lines in the design drawing is progressing | Alappuzha Project Dn AE4 | |
18 Sep 2021 | Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far. Marking of existing lines in the design drawing is progressing | Alappuzha Project Dn AE4 | |
15 Sep 2021 | Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far. Marking of existing lines in the design drawing is progressing | Alappuzha Project Dn AE4 | |
14 Sep 2021 | Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far. Marking of existing lines in the design drawing is progressing | Alappuzha Project Dn AE4 | |
13 Sep 2021 | Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far. Marking of existing lines in the design drawing is progressing | Alappuzha Project Dn AE4 | |
08 Sep 2021 | Pipe material procurement progressing. Third party inspection notice issued to M/s CIPET on 26/08/2021. Testing not conducted by m/s CIPET so far | Alappuzha Project Dn AE4 |